The construction process can be followed here:   2021  •  2020  •  2019  •  2018

  • 2018

    08.06.2018 - Start of the contract

  • 08.06.2018 - 12.02.2019 - Design phase

    Freire Shipyard in collaboration with the ship designer Rolls Royce Marine AS are designing the new research vessel.

    3D images:

    To the photo album

  • 21.11.2018 > 22.11.2018 | Tests

    First tests on scale model at the MARIN institute in the Netherlands.

    To the photo album

  • 2019

    04.02.2019 > 06.02.2019 | Tests

    Further tests with scale model at MARIN (roll-decay, bubble sweep down, resistance).

    To the photo album

  • 07.02.2019 | End of the design phase

  • 13.02.2019 | Start of steel cutting

    To the photo album

  • 14.02.2019 > 15.02.2019 | Tests

    Cavitation tests at MARIN.

  • 27.03.2019 | Keel-laying

    The keel-laying at Freire Shipyard.

    To the photo album

  • 15.05.2019 | Progress

    To the photo album

  • 15.06.2019 | Updated 3D images

    To the photo album

  • 17.07.2019 | Thrusters tunnels

    Thrusters tunnels are being installed. 28 blocks are already installed on the slipway.

    To the photo album

  • 05.08.2019 | Progress

    To the photo album

  • 14.08.2019 | Hull

    Installation of the last bottom block of the hull is completed.

    To the photo album

  • 05.09.2019 | FAT steering gear

    The factory acceptance test (FAT) of the steering gear is done at Kongsberg, Norway.

    To the photo album

  • 11.09.2019 | FAT gensets

    The factory acceptance test (FAT) of one of the gensets is done at Anglo Belgian Corporation nv (ABC) te Ghent.

    To the photo album

  • 08.10.2019 | FAT switchboards

    Factory acceptance test of the switchboards is done at Kongsberg Maritime facilities in Gdansk, Poland.

    To the photo album

  • 11.10.2019 | Installation gensets

    Installation of the gensets on the new RV Belgica.

    To the photo album

  • 08.11.2019 | Progress

    To the photo album

  • 27.11.2019 | Progress

    To the photo album

  • 29.11.2019 | FAT trawl winches

    Factory acceptance test of the trawl winches is done at Ibercisa in Vigo, Spain.

    To the photo album

  • 03.12.2019 | Installation of the bow thrusters

    To the photo album

  • 03.12.2019 | FAT arbor/emergency generator

    Factory acceptance test of the harbor/emergency generator is done at Progener in Vigo, Spain.

    To the photo album

  • 04.12.2019 | Installation of the drop keels

    To the photo album

  • 2020

    10.01.2020 | Installation

    Installation, amongst others, of the fishing winches and propellers.

    To the photo album

  • 16.01.2020 | Progress

    To the photo album

  • 23.01.2020 | Painting

    Painting of the hull in white has started.

    To the photo album

  • 28.01.2020 | Installation of the bridge

    To the photo album

  • 03.02.2020 | Installation of the funnel

    To the photo album

  • 11.02.2020 | First launch

    The future Belgian research vessel Belgica was launched for the first time on 11 February 2020 from the Freire Shipyard in Vigo, Spain. An important milestone following the keel laying, the equivalent of the laying of the foundation stone of a building, just under a year ago.
    Press Release

    To the photo album

  • 12.02.2020 | Progress

    To the photo album

  • 13.02.2020 > 20.02.2020 | FAT trawl winches and cranes

    Factory acceptance tests of the trawl winches and cranes are done at Ibercisa in Vigo, Spain.

    To the photo album

  • 24.04.2020 | Progress

    To the photo album

  • 30.04.2020 | Installation

    Installation of the A-frame.

    To the photo album

  • 20.05.2020 | Installation

    Installation of the T-frames and aft castles.

    To the photo album

  • 22.05.2020 | Progress

    To the photo album

  • 25.05.2020 | Installation

    Installation of the foreward mast.

    To the photo album

  • 05.06.2020 | SAT

    SAT (Sea Acceptance Test) of the RHIB.

    To the photo album

  • 11.06.2020 | FAT

    FAT of the LARS (Launch & Recovery System) piston corer and of the scientific deck machinery.

    To the photo album

  • 20.06.2020 | Progress

    To the photo album

  • 03.07.2020 | Progress

    To the photo album

  • 15.07.2020 | Start-up

    Start-up of the switchboards.

    To the photo album

  • 22.07.2020 | Progress

    To the photo album

  • 04.08.2020 | Start-up

    First start-up of one of the 3 ABC engines.

  • 09.2020 | Progress

    To the photo album

  • 10.2020 | Progress

    To the photo album

  • 11.2020 | Progress

    To the photo album

  • 07.12.2020 > 11.12.2020 | SAT part 1

    SAT (Sea acceptance test).

  • 09.12.2020 | Launch & recovery

    Launch & recovery RHIB.

    To the photo album

  • 2021

    22.01.2021 > 07.02.2021 | SAT part 2  

    To the photo album

  • 25.02.2021 > 01.03.2021 | SAT part 3  

    To the photo album


  • 03.12.2021 | Reception

    Reception of the RV Belgica in Vigo.


  • 13.12.2021 | Arrival

    The new research vessel Belgica arrived in Zeebrugge.
    She is ready to start her first scientific campaigns in January 2022.

    To the photo album